What happens to tasks when a new booking occurs?

Q: What happens to current tasks when a new booking occurs?

A: When a new booking occurs and a task needs to move days due to agree with the rules you have set, the task will be reset to the first day of the task window or today- whichever is later. The Staff assignments will be reset per the Task Rule. The Piece Pay and Estimated times will be also be reset per Task Rule.

For  example :  You've pre-assigned a Check Out Clean to Mary on the day of  checkout . During scheduling, you've also reassigned the clean to Joan 2 days after the checkout. A new booking comes in that checks in the day of that clean's checkout (creating a back to back).  This will cause the task to be moved back to the checkout day and also back to Mary.